Valued at $65 million, the project is one of Ahrens’ most significant mining infrastructure projects to date, delivering up to 1,080 new accommodation rooms in addition to the 496 existing rooms, and include new kitchen, dining, laundry and recreation facilities. Once complete, the expanded camp will house a 1,600-strong workforce and provide lasting benefits for BHP’s operations supporting future copper smelter construction in South Australia.
Lead Project Manager Judah Johnston said the development marks a major milestone for Ahrens Mining & Industrial Services’ SA-based Olympic Dam division.
“This is the biggest project our MIS OD team has been part of,” Judah said. “It’s a fantastic opportunity to showcase our design and construct capabilities and strengthen our long-term partnership with BHP.”
The expansion will transform what was once a temporary facility, originally constructed by Ahrens in 2020, into a permanent, full-scale village. The scope includes a dry mess dining hall, wet mess and recreation areas, gym and sports courts, an administration building, maintenance and linen storage, upgrades to site infrastructure, and landscaped communal spaces.
The village will provide modern, comfortable and well-equipped facilities that improve the day-to-day experience of FIFO workers. From the dining and recreation areas through to the admin and operations spaces, everything is being designed with amenity, functionality and longevity in mind.
A key differentiator in Ahrens’ successful bid was the use of permanent, in-situ steel structures rather than modular buildings.
“This approach not only gives us more design flexibility, but also provides greater value and durability for BHP,” Judah said. “It’s a great example of how we can leverage Ahrens’ in-house steel fabrication and construction expertise to deliver a smarter, more sustainable outcome.”

Judah said cost savings achieved through reusing existing infrastructure were also a major factor in winning the project.
“Our design and construct model allowed us to propose an efficient layout that made full use of the site’s existing power, water, sewer and civil infrastructure,” he said.
Design partners Tonkin Consulting and Lucid, who were involved in the original camp build, brought detailed knowledge of the site’s infrastructure and GGA architects helped shape a functional and visually appealing masterplan for the expansion.
The project is currently in the design phase, with completion expected in February 2026. Construction will begin shortly after, with the first accommodation buildings ready by mid-2026 and final handover scheduled for Q2 2027.
Ahrens will deliver the project in close partnership with Fleetwood, MPS Group and Ausco Modular, who will assist with modular components and temporary facilities to ensure smooth operations throughout construction.
“There’s a lot of coordination involved,” Judah said. “We’re working around an existing, operational village so communication and collaboration will be key.”
This project is the natural progression of the work Ahrens been doing with BHP in SA over the past five years, proving our ability to integrate design and construct into the mining environment.
Thanks to Judah, General Manager – Mining Services SA Josh Swigart, Major Projects Development Lead Ralph Slape and Project Coordinator Kelli Exindaris for their leadership and dedication in securing and driving this landmark project.